Translate

Bond Project Updates

Photo of the construction area in the soon to be new commons.  You can see the steps going up into the new entryway

Project Overview

On October 24, 2023, Dickinson voters approved a $69 million school bond referendum.

This investment will fund security updates to our elementary schools and major improvements to Dickinson High School, including:

  • A new three-story academic wing with modern classrooms — 122,000 sq ft of new space
  • A central commons area and cafeteria
  • Updates to the 1990s addition
  • Replacement of the current pod classrooms
  • New auditorium 

Timeline: Construction began spring 2025, with the new addition scheduled to open in January 2027.

  

Project Timeline

All timelines are based on the current construction schedule and may be adjusted as the project progresses.

Phase 1 – Complete
Early site work and utility relocation has been finished.

Phase 2 – In Progress
Construction of the new addition is underway and is expected to be completed in November 2026.

Phase 3 Summer 2026

  • Work will begin on several areas of the existing school, including:
  • Parking lot improvements
  • Installation of new air systems
  • Fire sprinkler installation
  • Updates to hallways and classrooms
  • Construction of a new special education suite

Phase 4 January 2027

  • Students will move into the new addition
  • Demolition of pod classrooms will begin
  • Renovation work will start in the administration area

Phase 5 –April 2027

  • Construction of a new bus loop
  • Demolition and renovation of the existing boiler room and kitchen

Summer 2027

  • The overall project is expected to be completed.

  

Local Contractor Participation

Our bond projects continue to create opportunities for trade partners from Dickinson, western North Dakota, and across the state.

  • At Heart River Elementary, all 5 trade partners were from western North Dakota, including 4 from Dickinson.
  • At Lincoln Elementary, all 9 trade partners are from North Dakota, including 7 from western North Dakota and 6 from Dickinson.
  • At Roosevelt Elementary, 20 total trade partners were involved, including 18 from North Dakota, 16 from western North Dakota, and 14 from Dickinson.

Dickinson High School Frequently Asked Questions

Additional Resources

 October 7, 2024 Design Presention

Please use the video below to walk through the site plan and design with Icon Artichectural Group.  The presentation begins at the 29:00 mark. 

 

  2023 Bond Page 

Please visit the 2023 Facilities Bond Vote archive page to learn more about the communicated bond projects.

 

This site provides information using PDF, visit this link to download the Adobe Acrobat Reader DC software.